Posted by: Pdfprep
Post Date: November 1, 2020
A project manager is assigned to a project that was previously managed by a peer project manager. The project manager identifies several modifications that were deployed prior to CCB approval.
Which of the following change control processes is being mismanaged?
A . Change validation with quality checks
B . Regression planning
C . Identify approval authority
D . Change implementation
Answer: D
Leave a Reply