Rather than sending emails to communicate all project information, the project manager:
✑ Makes telephone calls to key stakeholders for urgent information
✑ Sends emails for routine information
✑ Posts on the project intranet site for required but minimally used information.
Which of the following BEST represents what the project manager is doing?
A . Prioritizing based on personal preferences
B . Tailoring the method based on message content
C . Adjusting the method based on confidentiality constraints
D . Demonstrating concern for technological factors
Answer: B