Which of the following are principles of re-engineering?
I. Link parallel activities instead of integrating results
II. Put a decision point where work is performed
III. Capture info once at the source
IV. Treat geographically dispersed resources separately
A . I, III, & IV
B . I, II, & IV Only
C . I, II, & III Only
D . II, III, & IV Only
Answer: C
Explanation:
7 principles of re-engineering