A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project.
Which of the following are critical for the project manager to provide?
A . Cost, schedule, organizational chart, and risks/issues
B . Risks/issues, cost, RACI chart, and action items
C . Schedule, cost, risks/issues, and milestones
D . Action items, organizational chart, schedule, and NDA
Answer: C
Explanation:
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 326