PdfPrep.com

Which of the following activities should be performed during the selection and implementation of a testing tool?

Which of the following activities should be performed during the selection and implementation of a testing tool?

a) Determine whether the organisation existing test process needs to change.

b) Conduct a proof of concept.

c) Implement the selected tool on a project behind schedule to save time.

d) Identify coaching and mentoring requirements for the use of the selected tool
A . a, b and c.
B . b, c and d.
C . a, c and d.
D . a, b and d.

Answer: D

Exit mobile version