Which of the following activities is NOT a part of the implementation phase in Scrum?
A . Daily Standup Meeting.
B . Updating the Product Backlog.
C . Release Planning Meeting.
D . Creating deliverables.
Answer: C
Explanation:
Reference: http://blog.scrumstudy.com/exploring-the-implement-phase-of-a-scrum-project/