At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration.
Which of the following activities is done first?
A . Create Work Breakdown Structure (WBS)
B . Create Scope Baseline
C . Collect Requirements
D . Define Scope
Answer: D