Which of the following activities is appropriate to the test planning stage?
A . Analyzing the test basis
B . Assigning resources for the planned activities
C . Designing the test environments
D . Writing a test execution schedule
Answer: B
Which of the following activities is appropriate to the test planning stage?
A . Analyzing the test basis
B . Assigning resources for the planned activities
C . Designing the test environments
D . Writing a test execution schedule
Answer: B