A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits . The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced . The client is only focused on benefits.
Which of the following actions should the program manager take?
A . Focus on the internal stakeholders to ensure cost and schedule objectives are achieved.
B . Balance stakeholder needs through the use of trade-offs among the stakeholder groups.
C . Focus on the external stakeholders to ensure the intended benefits are achieved.
D . Conduct a stakeholder meeting to allow everyone to state their priorities.
Answer: D