PdfPrep.com

Which of the 5Cs of written communications does the project manager need to address?

The project manager released a report. A few stakeholders express the view that the report should not have been directed to them.

Which of the 5Cs of written communications does the project manager need to address?
A . Correct grammar and spelling
B . Concise expression and elimination of excess words
C . Clear purpose and expression directed to the needs of the reader
D . Coherent logical flow of ideas

Answer: C

Exit mobile version