Which Knowledge Areas include processes from the Closing Process Group?
A . Project Quality Management and Project Time Management
B . Project Scope Management and Project Risk Management
C . Project Stakeholder Management and Project Cost Management
D . Project Integration Management and Project Procurement Management
Answer: D