Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?
A . Project Integration Management
B . Project Communications Management
C . Project Information Management System (PIMS)
D . Project Scope Management
Answer: B