Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?

Posted by: Pdfprep Category: CAPM Tags: , ,

Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?
A . Organizational process updates
B . Quality metrics
C . Change requests
D . Quality control measurements

Answer: B

Explanation: