Which item is an input to the Define Activities process?
A . Schedule data
B . Activity list
C . Risk register
D . Scope baseline
Answer: D
Which item is an input to the Define Activities process?
A . Schedule data
B . Activity list
C . Risk register
D . Scope baseline
Answer: D