Peter, a Project Manager, has raised concerns about your Scrum Team’s productivity and progress towards the objectives.
Which is the best way to respond to Peter’s concerns?
A . Share the Product Backlog, the projections towards the release dates and ensure that Peter has access.
B . Show the Profit & Loss (P&L) report.
C . Share the current impediments.
D . Share the last stakeholder status report prepared by the Scrum Master.
Answer: A
Explanation:
One of the key pillars that support the empirical process control is Transparency. Transparency will help manage stakeholder expectations and allow the teams to effectively adapt if and when needed.