Which is part of the PRINCE2 definition of a project?
A . An undertaking that consists of at least two management stages
B . A description of what must be delivered in order to gain acceptance
C . The total of a plan’s products
D . A temporary organization that is created for the purpose of delivering business products
Answer: D