Which is NOT an objective of the Controlling a Stage process?
A . Implement actions to control the impact of risks that occur during the stage
B . Review the Business Case at regular intervals to assess the impact of changes that occur during the stage
C . Update the Business Case with any changes agreed with the Project Board
D . Coordinate the delivery of products as agreed in the Stage Plan
Answer: C