Which is a purpose of the Risk theme?
A . Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
B . Establish a cost-effective procedure to identify, assess and control uncertainty
C . Establish mechanisms to control any unacceptable deviations from plan
D . Establish mechanisms to manage risks at the corporate or programme level of an organization
Answer: B