Which is a purpose of the Managing Product Delivery process?
A . Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package
B . Provide a controlled link between the Project Manager and the Team Manager(s)
C . Enable the Project Board to request updates to the current Team Plan
D . Establish solid foundations for the project
Answer: B