Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?

Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?
A .  Feedback analysis
B .  Stakeholder analysis
C .  Communication management plan
D .  Stakeholder management plan

Answer: D