Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?

Posted by: Pdfprep Category: CAPM Tags: , ,

Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?
A . Issue log
B . Change log
C . Expert judgment
D . Change requests

Answer: B

Explanation: