Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?

Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
A .  Procurement documents
B .  Communications plan
C .  Project charter
D .  Stakeholder register

Answer: C