Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
A . Procurement documents
B . Communications plan
C . Project charter
D . Stakeholder register
Answer: C
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
A . Procurement documents
B . Communications plan
C . Project charter
D . Stakeholder register
Answer: C