Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?

Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
A . Procurement documents
B . Communications plan
C . Project charter
D . Stakeholder register

Answer: C

Explanation:

Process: 13.1 Identify Stakeholders

Definition: The process of identifying the people, groups,

or organizations that could impact or be impacted by a decision, activity, or

outcome of the project; and analyzing and documenting relevant information

regarding their interests, involvement, interdependencies, influence, and

potential impact on project success.

Key Benefit: The key benefit of this process is that it allows the project manager to identify the appropriate focus for each stakeholder or group of stakeholders.