Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
A . Procurement documents
B . Communications plan
C . Project charter
D . Stakeholder register
Answer: C
Explanation:
Process: 13.1 Identify Stakeholders
Definition: The process of identifying the people, groups,
or organizations that could impact or be impacted by a decision, activity, or
outcome of the project; and analyzing and documenting relevant information
regarding their interests, involvement, interdependencies, influence, and
potential impact on project success.
Key Benefit: The key benefit of this process is that it allows the project manager to identify the appropriate focus for each stakeholder or group of stakeholders.
Inputs
– Project charter
– Procurement documents
– Enterprise environmental factors
Organizational process assets
Tools & Techniques