Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?

Posted by: Pdfprep Category: CAPM Tags: , ,

Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?
A . Work performance data
B . Project documents
C . Scope baseline
D . Requirements documentation

Answer: B

Explanation:

Configuration control is focused on the specification of both the deliverables and the processes; while change control is focused on identifying, documenting, and approving or rejecting changes to the project documents , deliverables, or baselines.

Some of the configuration management activities included in the Perform Integrated Change Control process are as follows:

– Configuration identification. Identification and selection of a configuration item to provide the basis for which the product configuration is defined and verified, products and documents are labeled, changes are managed, and accountability is maintained.

– Configuration status accounting. Information is recorded and reported as to when appropriate data about the configuration item should be provided. This information includes a listing of approved configuration identification, status of proposed changes to the configuration, and the implementation status of approved changes.

– Configuration verification and audit. Configuration verification and configuration audits ensure the composition of a project’s configuration items is correct and that corresponding changes are registered, assessed, approved, tracked, and correctly implemented. This ensures the functional requirements defined in the configuration documentation have been met.

Leave a Reply

Your email address will not be published.