Which information from the risk register is used during the ‘assess – evaluate’ step to calculate the total risk exposure of an activity?

Posted by: Pdfprep Category: MORF Tags: , ,

Which information from the risk register is used during the ‘assess – evaluate’ step to calculate the total risk exposure of an activity?
A . Identified risks resulting from a risk response action
B . Estimated likelihood of the risks occurring
C . Exposure of the risks after completion of risk responses
D . The timeframe in which the risks are likely to occur

Answer: B