PdfPrep.com

Which hosting data center pair can host the new application?

Refer to the exhibit

ACME Mining has four data centres in Santiago, Cape town, Mumbai, and Beijing, full-mesh connected via a 400 Mb/s EVP-LAN.

They want to deploy a new mission-critical application with these requirements

• cluster heartbeat 2 Mb/s continuous (250 KB/s)

• cluster heartbeat one-way maximum latency 100 ms

These are the current ping tests results between the four data centers:

Which hosting data center pair can host the new application?
A . Santiago and Cape Town
B . Cape Town and Mumbai
C . Mumbai and Beijing
D . Santiago and Beijing
E . Cape Town and Beijing
F . Santiago and Mumbai

Answer: B