Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?
A . Project team
B . Focus group
C . Change control board
D . Project stakeholders
Answer: C
Explanation:
Change Control Board (CCB).
A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recording and communicating such decisions.