Posted by: Pdfprep
Post Date: November 21, 2020
Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?
A . Project team
B . Focus group
C . Change control board
D . Project stakeholders
Answer: C
Leave a Reply