Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

Posted by: Pdfprep Category: CAPM Tags: , ,

Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?
A . Project team
B . Focus group
C . Change control board
D . Project stakeholders

Answer: C

Explanation:

Change Control Board (CCB).

A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recording and communicating such decisions.