A project team member is estimating the cost of an activity and is checking documentation from previous similar projects.
Which estimation method is the project manager using to complete this task?
A . Bottom-up estimating
B . Three-point estimating
C . Analogous estimating
D . Parametric estimating
Answer: C
Explanation:
Reference: https://pm4id.org/chapter/9-1-estimating-costs/