PdfPrep.com

Which earned value management formula can help you determine how likely it is that you’ll complete the program based on the amount of cash left in the program budget?

Which earned value management formula can help you determine how likely it is that you’ll complete the program based on the amount of cash left in the program budget?
A . Estimate at completion
B . Variance at completion
C . To-complete performance index
D . Estimate to complete

Answer: C

Exit mobile version