Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?
A . Cost variance (CV)
B . Cost performance index (CPI)
C . Budget at completion (BAC)
D . Variance at completion (VAC)
Answer: B