Which document in the project management plan can be updated in the Plan Procurement Management process?

Which document in the project management plan can be updated in the Plan Procurement Management process?
A .  Budget estimates
B .  Risk matrix
C .  Requirements documentation
D .  Procurement documents

Answer: C