Posted by: Pdfprep
Post Date: November 15, 2020
Which document in the project management plan can be updated in the Plan Procurement Management process?
A . Budget estimates
B . Risk matrix
C . Requirements documentation
D . Procurement documents
Answer: C
Explanation:
Process: 12.1 Plan Procurement Management
Definition: The process of documenting project procurement
decisions, specifying the approach, and identifying potential sellers.
Key Benefit: The key benefit of this process is that it determines whether to acquire outside support, and if so, what to acquire, how to acquire it, how much is needed, and when to acquire it.
Inputs
Leave a Reply