Which describes the ‘Implement’ step within the recommended risk management procedure?
A . Project Support will allocate the risk budget to fund the selected risk responses
B . The risk owner will decide the best response to control the risk
C . The risk owner and the risk actionee will carry out activities to control and deal with the risk
D . The Project Manager will formulate the Risk Management Strategy
Answer: C