Which describes the ‘Identify Risks’ step within the recommended risk management procedure?
A . Identify responses to risks documented in the Business Case
B . Gather information about the project environment and objectives
C . Identify the roles to be involved in risk management activities
D . Identify uncertainties that may impact on the delivery of the project objectives
Answer: D