Refer to the exhibit.
A customer needs an AirWave solution that can manage 1000 devices. The customer wants a hardware solution and active/standby redundancy for the solution.
The exhibit shows the BOM that the architect has created.
Which corrections should the architect make?
A . Change the active appliance to an Enterprise appliance.
B . Add 1000 additional AirWave managed device licenses.
C . Change both of the appliances to Enterprise appliance.
D . Add a failover license for 1000 managed devices.
Answer: C