Which components of the project management plan are inputs used when creating the stakeholder engagement plan?

Which components of the project management plan are inputs used when creating the stakeholder engagement plan?
A . Risk, resource, and communications management plans
B . Scope, quality, and resource management plans
C . Procurement, integration, and risk management plans
D . Communications, schedule, and cost management plans

Answer: D