Which components of the project management plan are inputs used when creating the stakeholder engagement plan?
A . Risk, resource, and communications management plans
B . Scope, quality, and resource management plans
C . Procurement, integration, and risk management plans
D . Communications, schedule, and cost management plans
Answer: D