Which capability allows users to view variances in a project’s schedule?
A . Move project
B . Project Status Report
C . Compare scheduled baselines
D . Machine-learning algorithms
Answer: C
Which capability allows users to view variances in a project’s schedule?
A . Move project
B . Project Status Report
C . Compare scheduled baselines
D . Machine-learning algorithms