Which are examples of processes that may be used once or at predefined points in the project life cycle?

Which are examples of processes that may be used once or at predefined points in the project life cycle?
A . Develop Project Charter and Close Project or Phase
B . Define Activities and Acquire Resources
C . Control Schedule and Conduct Procurements
D . Monitor Communications and Control Costs

Answer: A

Explanation:

Reference: https://www.greycampus.com/opencampus/project-management-professional/closing-a­project-or-phase