Which are examples of processes that may be used once or at predefined points in the project life cycle?
A . Develop Project Charter and Close Project or Phase
B . Define Activities and Acquire Resources
C . Control Schedule and Conduct Procurements
D . Monitor Communications and Control Costs
Answer: A
Explanation:
Reference: https://www.greycampus.com/opencampus/project-management-professional/closing-aproject-or-phase