Which are examples of processes that may be used once or at predefined points in the project life cycle?

Posted by: Pdfprep Category: CAPM Tags: , ,

Which are examples of processes that may be used once or at predefined points in the project life cycle?
A . Develop Project Charter and Close Project or Phase
B . Define Activities and Acquire Resources
C . Control Schedule and Conduct Procurements
D . Monitor Communications and Control Costs

Answer: A

Explanation:

Reference: https://www.greycampus.com/opencampus/project-management-professional/closing-a­project-or-phase