Which answer best describes the topics covered in Sprint Planning?
A . What to do and who will do it.
B . How conditions have changed and how the Product Backlog should evolve.
C . What can be done and how to do it.
D . What went wrong in the last Sprint and what to do differently this Sprint.
E . Who is on the team and what team member roles will be.
Answer: C