MANAGING A STAGE BOUNDARY
The ABC Company trainers have been accredited and the course booking procedures have been amended. The ‘managing a stage boundary’ process is taking place at the end of stage 3 .
Which activity should occur during the ‘update the business case’ activity?
A . Update the overall plan with the time and cost taken to develop the ‘e-learning course’ and ‘amended course booking procedures’
B . Break the ‘planned pilot courses’ down into component products in order to identify the work required to deliver them.
C . Review whether the possible sales of the training course to external companies are likely to cover the project costs.
D . Review whether a new team manager should be appointed to lead the delivery of the pilot courses during stage 4.
Answer: A