Which activity includes addressing the disadvantages of ‘doing nothing’ to those stakeholders that object to the programme?
A . Analyse stakeholders
B . Sum ma rise risks
C . Carry out a health check
D . Conduct a visioning workshop
Answer: D
Which activity includes addressing the disadvantages of ‘doing nothing’ to those stakeholders that object to the programme?
A . Analyse stakeholders
B . Sum ma rise risks
C . Carry out a health check
D . Conduct a visioning workshop
Answer: D