PdfPrep.com

Which activities are critical for delivering Agile projects? There are 2 correct answers to this question.

Which activities are critical for delivering Agile projects? There are 2 correct answers to this question.
A . Retrospective agenda creation
B . Sprint planning
C . Release planning
D . Blueprint scheduling

Answer: B,C

Exit mobile version