Which action should the team manager take in response?


MANAGING PRODUCT DELIVERY

Stage 2 is in progress. While producing the team plan, the team manager responsible for the work package to develop the ‘classroom-based training material’ discovered that the representatives assigned to check the products were unsuitable.

Which action should the team manager take in response?
A . Discuss the situation with project assurance.
B . Advise the project manager of this risk.
C . Update the quality register with these concerns.
D . Raise an exception report to the project manager.

Answer: B