The senior user is concerned that the trainers’ limited availability could delay their accreditation. This was discussed during the ‘starting up a project’ process, but during the ‘initiating a project’ process the project manager notices that it has not been recorded.
Which action should the project manager take FIRST?
A . Add appropriate activities to the project plan to manage the concern and avoid any adverse impact.
B . Raise an exception report to manage the impact that any such delay would have on the project plan.
C . Raise an issue report so that the trainers’ time can be allocated to the accreditation activities.
D . Add the information to the risk register so that it can be evaluated and an action decided.
Answer: A