Which action is included in the Control Costs process?

Which action is included in the Control Costs process?
A .  Identify how the project costs will be planned, structured, and controlled
B .  Determine policies, objectives, and responsibilities to satisfy stakeholder needs
C .  Develop an approximation of the monetary resources needed to complete project activities
D .  Monitor cost performance to isolate and understand variances from the approved cost baseline

Answer: D