Which action is included in the Control Costs process?

Which action is included in the Control Costs process?
A . Identify how the project costs will be planned, structured, and controlled
B . Determine policies, objectives, and responsibilities to satisfy stakeholder needs
C . Develop an approximation of the monetary resources needed to complete project activities
D . Monitor cost performance to isolate and understand variances from the approved cost baseline

Answer: D

Explanation: